Project Details
Wind Farm
**
Location | Russell, MA |
Client | Holiday Hill Wind Farm |
Duration | 4 Months |
Project Summary
Holiday Hill Wind Farm
Project Facts
- Drilling & grouting of two 500’ grounding wells
- Site ground grid installation
- 25kv medium-voltage URD installation
- 2-2750kVa pad-mounted, oil-filled transformers
- 690v low-voltage feeders to wind turbine PCUs
- Power, control & fiber optic installation in two Goldwind 2.5MW wind turbines
- NETA ATS testing of transformers & 25kv cable/terminations installation