Project Details
Overhead/Underground Distribution (Solar Interconnect)
** Project Detail Summary **
Location | Littleton/Boxborough, MA |
Duration | 2 Months |
Project Summary
** Project Summary **
Offices
** Offices **
Services
Plan and Spec
Project Facts
- Installation of approx. 4,500’ overhead distribution on twenty-two 45’ Class 2 wooden poles
- Installation of all associated hardware, conductors, insulators, grounding & guying materials into rock & ledge
- Installation of 2-25kV gang-operated load break switches
- Installation of 1-25kV primary metering bank
- Providing and installation of 25kV URD feeders to pad mounted oil-filled transformers
- Completion of all terminations & grounding & providing of testing of 25kv cables & terminations to NETA acceptance testing standards