Project Details
AC-Coupled Energy Storage System
** Project Detail Summary **
Location | Amherst, MA |
Duration | 3 Months |
Project Summary
** Project Summary **
Project Facts
- Installation of 2-15kV medium-voltage URD circuits from existing vault to new energy storage system
- Installation of underground AC, DC & DAS conduits for BESS & balance of plant equipment
- Installation of site ground grid
- Installation of 1320kw PCS
- Installation of 49’ IHI battery energy storage container
- Installation of 360 Lishen batteries